Posted 30 January 2025, 5:01 am EST
Hi,
Our development team has confirmed that the End Date in the Gantt sheet is calculated automatically based on the task duration. This functionality is implemented by design, which is why it cannot be directly modified via the date-time dropdown and remains deactivated.
However, modifying the Start Date should automatically adjust the End Date accordingly and it seems to be an issue.
That said, our team is further investigating this behavior to ensure it functions as expected. We will keep you informed of any updates or changes regarding this matter.
We appreciate your patience and understanding.
Best Regards,
Ankit