This function returns the number of working days before or after the starting date.

Syntax

WORKDAY(startdate, numdays, [holidays])

Arguments

This function has these arguments:

Argument

Description

startdate

[Required] Date that is the starting date; a number (as in 37806.5), or a DateTime object, as in DATE(2003,7,4)

numdays

[Required] Number of non-weekend or non-holiday days before or after the starting date; days in the future are positive and days in the past are negative; if not an integer, the number is truncated

holidays

[Optional] Range of dates to exclude from the calculation; if omitted, the calculation assumes no holidays and all weekdays are workdays

Examples

WORKDAY(A2,A4)

WORKDAY(R2C1,R5C5)

WORKDAY(A1,A2,A5:A7)