Drag and Drop

You can now drag and drop a task to change the position of a row within tasks grid. It is also possible to select multiple rows and drag them.

A gif to show how you can drag and drop your tasks at run time.

To drag and drop a task, perform the steps given below:

  1. Select the task you wish to change its row position.
  2. Drag the selected task to the desired position where you wish to drop it.
  3. Drop the selected task above or below another task to reorder the row positions of tasks.
    This moves your task row to a new position.