A grid comprises of rows and columns to record information. A column generally contains information of the same type, whereas a row can contain information of different data types.
In GanttView, the collection of columns is represented by the ColumnCollection class which is accessible through the Columns property of the C1GanttView class.
This section walks you through different operations that can be performed on columns in the GanttView control.
You can add a column to the ColumnCollection by using the Columns property of the C1GanttView class. To add columns to the grid, please refer to the code snippet provided below.
C1.Win.GanttView.TaskPropertyColumn taskPropertyColumn1 = new C1.Win.GanttView.TaskPropertyColumn();
taskPropertyColumn1.Caption = "Duration";
taskPropertyColumn1.ID = 1437604830;
taskPropertyColumn1.Property = C1.Win.GanttView.TaskProperty.Duration;
this.c1GanttView1.Columns.Add(taskPropertyColumn1);
You can also add columns at run time. To add columns using the ColumnCollection of the GanttView, follow the steps below:
, to open the Grid Columns dialog box.GanttView allows you to move columns to occupy new position in the grid.

To move the column at run time, follow the steps below:
GanttView allows you to create custom columns as per your requirements. In GanttView, custom columns are represented by the CustomFieldColumn class. Other than this, you can also set various attributes of a custom column.
Below code snippet shows how you can create a custom column in the GanttView control.
CustomFieldColumn cc = new CustomFieldColumn();
cc.Caption = "My Numeric Column";
cc.DataType = typeof(decimal);
cc.Format = "$#0";
cc.Name = "MyNumericColumn";
cc.TextAlign = System.Windows.Forms.HorizontalAlignment.Right;
cc.Width = 65;
c1GanttView1.Columns.Add(cc);
A dropdown can be added to a custom column in the GanttView, as shown in the image below

To add a dropdown in custom column, follow the steps below:
Create an object of C1FlexGrid class and retrieve it as a child control of C1GanttView. This helps to access the custom column as an individual entity.
C1FlexGrid gridView = c1GanttView1.Controls[2] as C1FlexGrid;
Add BeforeEdit event using the object of C1FlexGrid class as shown in the below code:
gridView.BeforeEdit += GridView_BeforeEdit;
Create and add a ComboList to the custom column under the BeforeEdit event. The name passed for the grid column should match the caption of the custom column. In the following code, Task Priority is the caption of custom column and the values P1, P2, P3, and P4, are the values added to the combo list.
C1FlexGrid gridView = sender as C1FlexGrid;
gridView.BeginUpdate();
if (gridView.Cols[e.Col].Name == "Task Priority")
gridView.Cols[e.Col].ComboList = "P1|P2|P3|P4";
gridView.EndUpdate();
Rows and columns in GanttView control can easily be customized. GanttView enables you to select multiple rows or columns and customize them according to your needs. You can indent and outdent the selected tasks, delete the tasks, and change their field styles. You can also select several cells to change field styles for the selected tasks/fields. Other than this, you can highlight a particular task by changing the font color and background style for that task name.
To customize multiple rows and columns at the same time, follow the steps below:
Duration columns displays the total amount time taken to complete task. This is generally the length of time it takes to complete a task from beginning to end. You can show the duration columns in the grid by using the Duration and DurationUnits properties of the Task class.
To programmatically show/hide the values of the Duration and DurationUnits properties in the grid, add the code given below:
private void chkShowDuration_CheckedChanged(object sender, EventArgs e)
{
TaskPropertyColumn durationCol = c1GanttView1.Columns.Search(TaskProperty.Duration);
TaskPropertyColumn unitsCol = c1GanttView1.Columns.Search(TaskProperty.DurationUnits);
if (durationCol != null && unitsCol != null)
{
bool visible = chkShowDuration.Checked;
durationCol.Visible = visible;
unitsCol.Visible = visible;
}
}