You can easily change the fore color of the grid, highlighted cell, and even the fixed cells. This section discusses how you can customize the fore color of various elements in the GanttView.

You can set the fore color of the entire grid by using the GridForeColor property of the C1GanttView class.
Below code snippet shows how you can set the fore color of the entire grid in the GanttView.
//Set fore color of the grid
c1GanttView1.GridForeColor = Color.DarkGreen;
To set the fore color of the fixed cells, use the FixedForeColor property of the C1GanttView class.
Below code snippet shows how you can set the fore color of the fixed cells.
//Set fore color of the fixed cells
c1GanttView1.FixedForeColor = Color.DarkBlue;
To set the fore color of the highlighted cell in the grid, use the HighlightForeColor property of the C1GanttView class.
Use the below code snippet to set the fore color of the highlighted cell.
//Set fore color of the highlighted cell
c1GanttView1.HighlightForeColor = Color.Red;