GanttView lets you customize the border of the entire grid as well as individual cells by changing border style, color, and so on.

You can use the BorderStyle property which takes BorderStyle enumeration as an input to set the border style of the grid.
Below code snippet shows how you can customize the border style of the entire grid.
//Set the border style of the grid
c1GanttView1.BorderStyle= BorderStyle.FixedSingle;
To customize the border color of all the cells in the grid, you can use the CellBorderColor property of the C1GanttView class.
Below code snippet shows how you can customize the border color of the cells in the GanttView control.
//Set the border color of cells
c1GanttView1.CellBorderColor= Color.Blue;
Fixed cells refer to those cells which appear in the top row and the left-most column of the grid. You can customize the border color of these fixed cells by using the FixedCellBorderColor property of the C1GanttView class.
Below code snippet shows how you can customize the border color of the fixed cells in the GanttView control.
//Set the border color of the fixed cells
c1GanttView1.FixedCellBorderColor= Color.Green;